DBIA: Principles of Design-Build and Post Award & Contracts Test 100% VERIFIED SOLUTIONS 2023//2024
DBIA: Principles of 
Design-Build and Post 
Award & Contracts 
Test 100% VERIFIED 
SOLUTIONS 
2023//2024 
Miller Act 1935 - ANSWER Federal Government passed bond requiring payment and 
performance bonds on all public works, what year? 
Brooks Bill 1972 - ANSWER Bill directing A/E's selected on qualifications, what year? 
Clinger Cohen Act/Defense Procurement Reform Act 1996 - ANSWER Allows all 
federal agencies to utilize Design-Build. Prior to that no enabling legislation existed 
allowi...
- Package deal
- Exam (elaborations)
- • 9 pages •
DBIA: Principles of 
Design-Build and Post 
Award & Contracts 
Test 100% VERIFIED 
SOLUTIONS 
2023//2024 
Miller Act 1935 - ANSWER Federal Government passed bond requiring payment and 
performance bonds on all public works, what year? 
Brooks Bill 1972 - ANSWER Bill directing A/E's selected on qualifications, what year? 
Clinger Cohen Act/Defense Procurement Reform Act 1996 - ANSWER Allows all 
federal agencies to utilize Design-Build. Prior to that no enabling legislation existed 
allowi...
DBIA Test VERIFIED SOLUTIONS 2023//2024
DBIA Test VERIFIED 
SOLUTIONS 
2023//2024 
Project Delivery System - ANSWER How team members are organized, establishes 
when parties engage, determines roles of parties, and determines sequence of design, 
procurement, and construction (db, cmar, dbb) 
Procurement Method - ANSWER how team members are selected (QBS, best value, 
low price, sole source) 
contracting approach - ANSWER how team members are paid (fp, gmp, cost 
reimbursement, target price, unit price) 
Design-Bid-Build (DBB) - ...
- Package deal
- Exam (elaborations)
- • 11 pages •
DBIA Test VERIFIED 
SOLUTIONS 
2023//2024 
Project Delivery System - ANSWER How team members are organized, establishes 
when parties engage, determines roles of parties, and determines sequence of design, 
procurement, and construction (db, cmar, dbb) 
Procurement Method - ANSWER how team members are selected (QBS, best value, 
low price, sole source) 
contracting approach - ANSWER how team members are paid (fp, gmp, cost 
reimbursement, target price, unit price) 
Design-Bid-Build (DBB) - ...
DBIA Test 100% VERIFIED SOLUTIONS 2023//2024
DBIA Test 100% 
VERIFIED SOLUTIONS 
2023//2024 
Project Delivery System - ANSWER How team members are organized, establishes 
when parties engage, determines roles of parties, and determines sequence of design, 
procurement, and construction (db, cmar, dbb) 
Procurement Method - ANSWER how team members are selected (QBS, best value, 
low price, sole source) 
contracting approach - ANSWER how team members are paid (fp, gmp, cost 
reimbursement, target price, unit price) 
Design-Bid-Build (DBB...
- Package deal
- Exam (elaborations)
- • 11 pages •
DBIA Test 100% 
VERIFIED SOLUTIONS 
2023//2024 
Project Delivery System - ANSWER How team members are organized, establishes 
when parties engage, determines roles of parties, and determines sequence of design, 
procurement, and construction (db, cmar, dbb) 
Procurement Method - ANSWER how team members are selected (QBS, best value, 
low price, sole source) 
contracting approach - ANSWER how team members are paid (fp, gmp, cost 
reimbursement, target price, unit price) 
Design-Bid-Build (DBB...